Grid access · resource ledger

Interconnection Queue

AI did not create the five-year generation queue, but it is forcing a separate large-load reckoning.

Scapegoated5 yearsmedian request-to-operation time for projects built in 2023

What the evidence supports

LBNL found a five-year median for generation projects completed in 2023, with nearly 2,600 GW waiting—over 95% zero-carbon resources. That structural backlog predates today’s AI wave. FERC is now separately reforming large-load connection rules.

Mechanism
Generation queues study projects supplying the grid; large-load processes study customers drawing from it. They interact, but collapsing them into one ‘AI queue’ is a category error.
Who pays—or gains
Delayed generators, large loads and ultimately customers pay for slow studies and network upgrades. Better queue management is a supply-side reform with broad benefits.
Binding constraint
Study throughput, speculative projects, transmission planning, cost allocation and incomplete tariff rules for flexible or co-located loads.
Strongest caveat
The scapegoated grade applies to the claim that AI caused the existing five-year generation queue—not to the claim that new data centers add grid work.
What would change the grade
Regrade if comparable queue data show AI-driven large-load studies displacing generation projects or materially lengthening completion times.

Evidence file

Primary and first-party sources

  1. Queued Up: 2024 EditionLawrence Berkeley National LaboratoryPublished 2024-04 · checked 2026-07-16
  2. FERC launches targeted action to speed large-load integrationFederal Energy Regulatory CommissionPublished 2026-06-18 · checked 2026-07-16